Hutto ISD voters approved a $194 million bond proposal on May 4th that includes projects in safety & security, growth, and equity. The district also created a Bond Oversight Committee to oversee the May 2019 Bond.
Safety & Security
-
$500,000
Upgrades to Department of Health and Safety server capacity and retrofit/additions projects concerning intrusion detection, fire alarm systems, access controls, security cameras systems, and communication systems.View Safety & Security Projects
Growth
-
$29,400,000
Cottonwood Creek ES, Nadine Johnson ES, Ray ES, Veteran’s Hill ES Projects
Replace classroom & Library furniture, Replace HVAC (except NJES which was replaced in 2018 and VHE) Replace HVAC Controls (except NJES which was replaced in 2018), Roofing and Building Façade repair and improvements. -
$77,760,000
Fine Arts Additions (Ballet Folklorico & Orchestra), PBL learning space renovations, Replace classroom & Library furniture, Replace HVAC, Replace HVAC Controls, Roofing and Building Façade repair and improvements
New Middle School #3 Construct new 1200 student Middle School on district-owned property adjacent to Kerley ES to support growth west of TX SH-130 and along the 130 corridor. Site will be organized similarly to HMS/CCES & FMS/RES. Design will be a new prototype, approximately 160,000 s.f.
-
$60,800,000
Band, Choir, Orchestra and Theater Additions & Renovations, Career & Technical Education (CTE) program Additions & Renovations, Replace some HVAC, Replace HVAC Controls, Roofing and Building Façade repair and improvements, Baseball & Softball Field Lighting Upgrades, Stadium Additions & Renovations
-
$5,000,000
New facility with shops and repair bays, driver training facility, and increased parking capacity- to include minor modifications to existing maintenance and warehouse facilities.
-
$16,535,000
Immediate needs include Security System Upgrades, Disaster Recovery Systems, Fiber WAN, and Replace Switches. 2-4 Year Needs include Renovations to Technology closets, Structured Cabling, Wireless Improvements, Classroom AV Upgrades and Data Center Improvements.
-
$3,000,000
if needed….for possible costs associated with land purchases and site development for future school sites
-
$1,400,000
New fleet purchases, buses, white fleet, and heavy equipment per fleet replacement plan.
Equity
-
Hutto Elementary School Modernization
Demolish original 15,427 s.f. classroom building. Construct new, two-story, 26,000 s.f. addition to house 21 classrooms, 1 music room, and administrative space. Major renovation of existing 12,264 s.f. building into a larger media center and 4 larger classrooms. Major renovations of existing 9,737 s.f. serving, kitchen, and administration building. Minor renovations of remaining 27,500 s.f. to improve dining area, gymnasium, and classroom wing constructed in 1990s.